Here’s the Latest Progress of Hangzhou Asian Games Village
en.hangzhou.com.cn   2021-06-24 11:55   Source:Hangzhou Daily

An oath-taking meeting under the theme of “Complete the construction of Hangzhou Asian Games Village within six months” was held at the construction site of the project on the morning of June 23. The Asian Games Village consists of athlete village, technological official village, media village, international zone and public zone. 45.0% of the refined decoration, 71.6% of the exterior decoration, 83.5% of the mechanical and electrical installation, and 48.5% of the municipal landscape of the three villages and four zones have been finished. All units involved are sparing no effort to accelerate the project to “finish it before the end of 2021”.